Harbor Drive Trunk Sewer City of San Diego.
About 4,231 lineal feet of 48-inch PLRCP trunk sewer along Harbor Drive, from Beardsley Street to 28th Street.
- Project
- Harbor Drive Trunk Sewer
- Client
- City of San Diego
- Project type
- Sewer / Water / CIPP / Jack & Bore / HDD & Bypass
The work involved furnishing all labor, materials, equipment, services and construction for the installation of approximately 4,231 lineal feet of 48” PLRCP trunk sewer main along the east-bound lanes of Harbor Drive from Beardsley Street to 28th Street. Street sewer crossing connections included 21”, 18”, 15”, 12”, 10” and 8” sewer mains with PVC T-Locked manholes.
An additional 427 lineal feet of 48” PLRCP were installed inside a 66” diameter steel casing by jack and bore in two locations, to avoid existing utilities and to cross under the railroad tracks. A dual 30” HDPE (SDR-9) siphon pipe was installed by horizontal directional drilling, running 232 lineal feet under the 28th Street intersection.
The project also included abandonment of the existing 39” trunk sewer, two 42” siphons, two 36” siphons and 21” to 6” sewer mains, and the trenchless rehabilitation of 1,550 lineal feet of existing 48” trunk sewer. A series of dewatering wells and treatment tanks drew the ground water table down to workable limits, and a section of 12” CML&C water main for WG 525B was built in coordination with the City and Orion Construction.
A detailed, well-planned and executed sewer bypass system handled approximately 13.96 MGD of raw sewer throughout the project without any spills.
- License #718202 · Class A General Engineering
- C36 plumbing license
- Family owned since 1994
- 200+ public & private projects
From bid to restoration.
Teamwork, effective communication and hard work, so jobs are completed accurately, on time and within budget.
- 01
Bid & estimate
Send the plans and bid documents. Our estimating team prices the underground scope.
- 02
Plan & permit
Potholing of existing utilities, permits, traffic control and storm water pollution prevention plans.
- 03
Build
Trenching, shoring, dewatering, pipe, bedding and backfill, with bypass systems to keep service running.
- 04
Restore & close out
Connections to the existing system, trench resurfacing and site restoration, on time and within budget.
Planning a similar pipeline project?
Sewer, water, storm drain and CIPP lining, in public and private works. Office hours Monday–Friday, 6am to 4pm.
Have an underground project?
Call the office in Vista, Monday to Friday from 6am to 4pm, or send us a message. Wherever and whenever you need us, we are available to complete the job.